Triton Square Project

Latest News

NDS recently carried out the installation of 6NO cooling towers at the Triton Square project in Euston London.

Each cooling tower was delivered to the site in 4NO sections with each section weighing between 1500kg-2000kg.

The cooling tower sections were offloaded by the site lifting team using the tower crane on site.

NDS had 2NO complete cooling towers (8no sections) delivered to the site over a three day period and each section was placed into position at the roof level and assembled by the NDS site installation team.

The 6NO cooling towers and associated access walkways and gantries were installed and completed over a period of 5 working days.

All installation works & lifting requirements were successfully carried out within the programmed time constraints.