The City North Project
Projects
The City North Project
NDS lifted and plant moved a packaged plantroom at the City North project in Finsbury North London.
The packaged plantroom was 7000mm x 1800mm 2250mm and had a gross weight of 5000kg.
It was delivered to the site at 7.00 am, lifted using a MOD 24 spreader beam and landed onto a purpose built scaffold gantry. The packaged plantroom was then plant moved into its final location on a purpose built steelwork platform by NDS specialist plant movement team.
All lifting and plant movement works were carried out and completed within the allocated & agreed time constraints on site.